Wednesday report.

We are done with twelve courses all the way around.  We will need to pour in the morning and get three more courses done on the sides to get done on time.   Team is doing great and we have had very little rain.  We did have a mixer malfunction today.   Had to take it apart. Recruited ray to help disassemble.  